Israeli developer Enlight has delivered first power from its 105MW Blacksmith mega-farm in Serbia.
The company said it has a “connection confirmation” agreement with authorities with electricity being generated following ‘hot tests’ of turbines.
Advertisement
Revenues will be banked at 50% of the full electricity price, said Enlight.
Thirty-four of 38 GE 2.75MW turbines are installed at the wind farm, which is located in the north-east Vojvodina region.
Full operations are expected to get underway in the second quarter of 2019.
Blacksmith will generate revenue of €28m per year, according to Enlight.