Copenhagen Infrastructure Fund has chosen Taiwanese company Teco Electric for a turnkey contract for the onshore substation for the 542MW Changfang and 48MW Xidao offshore wind farms off the coast of the Asian island.
Teco and CIP will work together with the midstream and downstream suppliers to buy the main power equipment to ensure local content in the substation.
Advertisement
Teco will also provide some of the electrical equipment itself.
The first 100MW phase of Changfang is due online in 2021, with the remaining 452MW to be operational in 2023.
Xidao is expected online in 2024.
Both projects will feature MHI Vestas hardware.