Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » European onshore fleet ‘needs 65GW upgrade’
Onshore Wind

European onshore fleet ‘needs 65GW upgrade’

Robin LancasterBy Robin LancasterSeptember 9, 20194 Mins Read
Black & Veatch scrutinises UK clean power

A total of 65GW of European onshore wind turbines will need upgrading or replacing by 2028, according to new research from Wood Mackenzie.

The ‘European Onshore Wind Lifetime Extension Outlook’ report finds that from 2019 to 2028, an average of 4GW of turbines a year that are reaching end-of-design-life will be what it calls “lifetime extension (LTE) suitable”.

Advertisement

But, while upgrading components to extend the life of a turbine – the LTE option – is cheaper than alternative options available, not all asset owners will choose to implement this solution, Wood Mackenzie said.

Wood Mackenzie principal analyst Daniel Liu said: “The decision to extend the operational lifetime of turbine assets depends on asset owner strategies, project economics and site and turbine operating conditions.

“Distributed sites – those with three or less turbines – are economically less suitable for operating beyond design lifetime with considerable refurbishment and/or upgrade work.

“Larger sites need to balance regulatory issues, financial risks, technical challenges and operational challenges to make lifetime extensions economically viable.”

The report said options available to wind farm owners to maintain the existing capacity of the European onshore wind turbine fleet include complete repowering of projects.

However, the costs of new technology, permitting issues, regulatory hurdles and asset owner resources make repowering a “daunting proposition” for many operators, it added.

LTE is an alternative to decommissioning or complete repowering, said Wood Mackenzie.

Liu said: “We have identified 42GW of turbines reaching end-of-life by 2028 that have a commercially available LTE solution.”

Wood Mackenzie added that the leading onshore wind markets in Europe – Germany, Spain, UK and France – are unlikely to meet 2020 renewable energy targets and so new regulation is needed to prevent wholesale removal of wind generation capacity.

Providing regulatory support for LTE projects is one way to preserve existing capacity, it said.

“Currently, minimal regulatory support is offered for repowered and LTE projects, forcing asset owners to operate in a merchant power market,” said Liu.

“However, the introduction of the post-2020 Renewable Energy Directive should provide clarity for asset owners to decide on whether to decommission, repower, or extend the lifetime of their onshore wind assets.”

The report added that the success of the LTE strategy requires balancing and mitigating a number of risks.

Just under half of LTE-suitable turbines are situated on small or distributed project sites.

Liu said: “Project and supply chain economics mean that small and distributed sites are less ideal candidates for extensive turbine refurbishment and component upgrades as part of the LTE solution.

“Asset owners can potentially operate these turbines beyond the original design lifetime with minimal upgrades if sufficient operating reserves remain.”

He added that LTE for onshore wind is still in its infancy and upgrade packages offered for turbine classes are not a one-size-fits-all solution either.

“It’s too early to assess the operational longevity of turbines with an implemented LTE solution,” Liu said.

“More sophisticated and complex refurbishment, upgrade and operations packages will increase the post end-of-life operational lifetime but need to be balanced against costs.”

He said that depending on the level of retrofits and upgrades performed on a turbine, LTE solutions can be costly.

Older turbines also require higher maintenance spending as the risk of capital component failures rise, the analyst said.

“Insurers will price the risk of running older turbines past design-lifetimes, which could see premiums rise,” he added.

Such costs must be weighed up against the revenues in a merchant power market, Wood Mackenzie said.

Energy trading or corporate power purchase agreements could be implemented to provide cash flow security, it said.

Liu said: “Capital component failures remain the biggest operational risk and can be costly enough to eliminate the economic impact of running lifetime extended assets.

“Supply of spare parts may also be a concern for less popular technologies or from defunct OEMs.”

Onshore Wind Wood Mackenzie
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleTekmar covers Changhua wires
Next Article German consultancy offers Vattenfall advice

Related News

Solar maintenance to ‘cost $9.4bn by 2025’

June 22, 2020

PV ‘repowering potential to hit 67GW’

February 4, 2020

Onshore O&M costs ‘close to $15bn in 2019’

June 3, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}