Siemens is to supply three onshore wind projects in Scotland totalling 126MW.
The German manufacturer will construct, install and commission for ScottishPower Renewables 23 D3 direct drive 3MW turbines for the Dersalloch wind farm in South Ayrshire.
Installation is set to start in spring 2016, with handover expected in the autumn of that year.
Siemens also has a service contract for the wind farm.
It will supply six SWT-2.3MW 93 units for the Ewe Hill Phase One project in Dumfries and Galloway. A further 16 turbines will be installed for phase two.
Phase one installation will be in the spring next year and phase two in the autumn.
The third project is the Millour Hill community wind farm, which will be boosted by an additional two SWT 3.2MW 101 units on top of the existing six 3MW turbines already installed. The deal also includes maintenance.
Image: a Siemens direct drive turbine (Siemens)