Enefit Green has taken the final investment decisions on two wind farm projects in eastern Europe.
The Sopi-Tootsi project in Estonia will have 255MW of capacity and the Kelme I project in Lithuania will have 80MW of capacity.
Advertisement
The projects are part of Enefit Green’s previously presented investment plan, which aims to quadruple its electricity production capacity to the level of 1900MW by the end of 2026.
Over next two years Enefit Green will invest nearly €450m in these wind farms, while previous investments in these projects total €77m.
Enefit Green has four wind farms and three solar parks in Lithuania, Estonia, Poland and Finland under construction with a total capacity of 258MW.