Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Ireland, NI set to miss 2030 renewables targets
Other News

Ireland, NI set to miss 2030 renewables targets

SaraBy SaraAugust 6, 20242 Mins Read
Glennmont scores double wind sell-off

Ireland and Northern Ireland’s ambitious goals of generating 80% of their electricity from renewable sources by the end of this decade, will be delayed until at least 2032, says Cornwall Insight.

The data included in the Single Electricity Market Benchmark Power Curve reveals that by 2030 only 70% of the power grid will be using renewable sources, with the majority of the remaining electricity generated by gas plants.

Advertisement

While the 80% target set by both the Irish and Northern Irish governments is likely to be missed, significant progress has been made, with the SEM currently having the highest contribution of wind generation of any power system in the world.

Forecasts also predict a substantial increase in the percentage of electricity from renewables, rising from just over 40%1 in 2023 to 82% in 2032, highlighted Cornwall Insight.

Despite the successes, the 2030 target, included all Irelands Climate Action Plans since 2021, has encountered several challenges.

Chief among these are delays in planning and a shortage of grid connections.

These issues have been significant barriers for generators submitting bids in the Renewable Electricity Support Scheme (RESS) auction, which resulted in only three successful onshore wind projects last year.

Concerns over a lack of procured onshore wind projects have been increased by the announcement that the RESS4 auction, the final auction to procure generation coming on the grid prior to 2030, will see a lower onshore wind auction price cap. This is likely to deter bidders.

Other barriers to meeting the target have been raised by Wind Energy Ireland who recently warned that dozens of wind farms will be forced to shut down before the end of the decade if their planning permission timeline cannot be extended, potentially causing further delays to all Ireland’s renewables transition.

While there are still many obstacles to reaching the renewables target, there have been some positive steps forward for the RESS scheme.

Changes include allowing generators to delay their required operational date by up to two years if systems operator grid connection issues or judicial reviews of planning permissions arise, which it is hoped will increase the number of renewables bids.

In further positive news, stated Cornwall Insight, Northern Ireland is designing its own renewable support scheme, aiming to boost renewable energy projects.

The first auction is anticipated for 2025/26, but much of the procured capacity is expected to come online after 2030.

Cornwall Insight Other News SEM
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleElements Green reveals 800MW PV scheme feedback
Next Article Leadership changes at CS Wind Offshore

Related News

RESS 4 auction ‘misses 2030 targets’

September 16, 2024

Cornwall makes case for Celtic Sea power line

April 21, 2023

Northern Irish green goals ‘need onshore support’

August 10, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}