Browsing: Changhua 1&2a
Orsted confirms 900MW project will not be ready this year amid COVID-19 delays
CTCI Machinery Corporation has completed the manufacture and acceptance of second batch of pin piles for the 600MW, 62-turbine Changfang &…
Subcontractor will carry out the pre-assembly scope for the project’s Siemens Gamesa turbines
Work to install 111 structures and two offshore substations at 900MW project will take place in 2021 and 2022
Consultancy WSP contracted by Orsted to provide services for the 900MW offshore wind farm off Taiwan
South Korean company says subsea cables will be delivered by 2021
Orsted’s 900MW project will feature the Asia-Pacific variant of the 8.0-167 DD machine
Atos will supply communications technology to Orsted under a frame agreement for APAC offshore wind projects