Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » GE upgrades DolWin3 offshore grid
Grid

GE upgrades DolWin3 offshore grid

reNEWS EditorialBy reNEWS EditorialOctober 13, 20202 Mins Read
GE upgrades DolWin3 offshore grid

GE Renewable Energy’s Grid Solutions business has successfully upgraded the offshore grid connection DolWin3 in the North Sea.

The upgrades included enhancements to the valves and control system. In addition to improving the overall performance of the grid connection system, the upgrades also reduce maintenance.

Advertisement

Located approximately 80 kilometers from land, DolWin3 with the offshore converter platform DolWin gamma connects the wind farms Merkur Offshore, containing 66 Haliade 150-6MW GE Renewable Energy wind turbines, and Borkum Riffgrund 2 in the south-western part of the German North Sea with the onshore transmission grid.

“The offshore grid connection DolWin3 has been transferring power from wind generation in the North Sea to the German grid since the third quarter of 2018,” said TenneT large projects offshore director Marco Kuijpers.

“The updates that have recently been tested and certified give us confidence that our grid connection will still be stable and reliable in the future as we move toward our ultimate renewable energy goals in the future.”

The DolWin3 project uses Voltage Source Converter (VSC) technology, the newest HVDC technology featuring highly specialized power electronics, which allow for enhanced operational capability, greater power and frequency control, compared with line commutated converter (LCC) technology.

“The completion of the final certification tests for DolWin3, along with our recent award of the Sofia HVDC link, are further evidence that GE’s Voltage Source Converter technology is now well established and that GE has the ability to commercially deliver on these solutions,” said GE’s grid integration solutions head Raj Iyer.

“The DolWin3 upgrades incorporate learnings from our recently released industry leading second-generation VSC valve and eLumina control system.”

In July 2017, the heart of the DolWin3 grid connection, the DolWin gamma converter platform, was installed at sea.

The platform, built in Warnemünde, Mecklenburg-Western Pomerania, covered a six-day journey along the German and Danish coasts to its final location in the North Sea. Just over one year later, in the third quarter of 2018, the 900-megawatt (MW) grid connection was put into operation, supplying more than one million households with clean wind energy.

“HVDC technology plays a major role in supporting the long-term growth of the renewable energy industry throughout the world. We are proud to work together with visionary customers like TenneT to enable millions of people access to clean energy thanks to our technology,” added Iyer.

DolWin3 GE Grid
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticlePGE sifts bids for Baltica 2&3 studies
Next Article Mayflower Wind looking into hiring Shell workers

Related News

GE Vernova expands UK HVDC facilities

September 25, 2024

Prysmian wraps up DolWin3 link

November 13, 2019

ABB, Aibel to deliver Dogger Bank platforms

October 30, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}